Redcar Central Station
Welcome to the Redcar Central Station information and marketing page.
Redcar Central Station is a Grade II listed Victorian station and train shed built in c1860 for the extension coastwards of the Stockton-Darlington railway. It was last in use as a business centre which closed in 2013 and has not seen railway use since the late 1980s.
Redcar and Cleveland Borough Council have agreed a long lease of the building from the Arch Company, a new organisation that purchased the majority of Network Rail's commercial properties in 2017.
The plans viewable here will see the Station building and train shed sympathetically restored to its former glory. We are exploring potential uses for the revamped station but expect a mix of daytime and evening uses such as:
Rail uses - Covered waiting area, automatic ticket machines, rail and other live transport information
Bar, restaurant, shops, café, flexible spaces, markets, events, community activities, flexible workspaces, Toilets (including accessible spaces and changing facilities).
If you are interested in taking space in the building please contact Gavin Black on 0191 232 7030.
Welcome to the Redcar Central Station information and marketing page.
Redcar Central Station is a Grade II listed Victorian station and train shed built in c1860 for the extension coastwards of the Stockton-Darlington railway. It was last in use as a business centre which closed in 2013 and has not seen railway use since the late 1980s.
Redcar and Cleveland Borough Council have agreed a long lease of the building from the Arch Company, a new organisation that purchased the majority of Network Rail's commercial properties in 2017.
The plans viewable here will see the Station building and train shed sympathetically restored to its former glory. We are exploring potential uses for the revamped station but expect a mix of daytime and evening uses such as:
Rail uses - Covered waiting area, automatic ticket machines, rail and other live transport information
Bar, restaurant, shops, café, flexible spaces, markets, events, community activities, flexible workspaces, Toilets (including accessible spaces and changing facilities).
If you are interested in taking space in the building please contact Gavin Black on 0191 232 7030.
-
Drop-in session @ Rediscover Redcar - 8 November
Share Drop-in session @ Rediscover Redcar - 8 November on Facebook Share Drop-in session @ Rediscover Redcar - 8 November on Twitter Share Drop-in session @ Rediscover Redcar - 8 November on Linkedin Email Drop-in session @ Rediscover Redcar - 8 November linkYou are invited to attend drop-in sessions about the project on 8/11/24 from 11am-6pm @ Rediscover Redcar, 12 West Terrace, Redcar, TS10 1DS.
This is an opportunity to meet members of the project team, see up-to-date progress photos, plans and ask any questions you may have.
-
Construction Update - 17 October 2024
Share Construction Update - 17 October 2024 on Facebook Share Construction Update - 17 October 2024 on Twitter Share Construction Update - 17 October 2024 on Linkedin Email Construction Update - 17 October 2024 linkWorks are continuing to progress well on the project. All external scaffolds are nearing completion. The roofs to all building are in the process of being stripped ready for repair works.
Internally, demolition continues to the rooms on the first floor.
The work trackside (scaffolding and repairs) are continuing to progress. Network Rail have been carrying out essential track maintenance meaning a few Saturday night work shifts have been cancelled. Work will be ongoing on Saturday evenings between 11:30pm and 08:45am. We apologise for any disturbance from these works.
-
Saturday night working
Share Saturday night working on Facebook Share Saturday night working on Twitter Share Saturday night working on Linkedin Email Saturday night working linkIn order to carry out works to the roof and trackside elevations we are required to work with Network Rail to book possessions of the railway lines outside of operational hours. This is restrictive as we have both passenger and goods traffic on this route through the day and night so the only option we have is for Saturday night working.
Whilst we will look to minimise noise and disruption from the works at all times we are aware that night-time working is more disruptive. We apologise for this and ask that you please bare with us.
If you do have any questions or feedback about this working please contact the team using the details provided on this page.
Thank you.
-
Construction begins on Redcar Central Station
Share Construction begins on Redcar Central Station on Facebook Share Construction begins on Redcar Central Station on Twitter Share Construction begins on Redcar Central Station on Linkedin Email Construction begins on Redcar Central Station linkConservation works to transform it from an empty, dilapidated building into a vibrant, more welcoming gateway to the town will begin Monday 20 May.
The building will function both as a leisure and retail hub as well as a key transport link, providing rail facilities including ticket machines, travel information and covered waiting areas as well as food and drink outlets throughout the day and evening.
The project, which is funded by the Government’s Levelling Up Partnership Fund, Welcome to Redcar and Cleveland fund administered via Tees Valley Mayor and Combined Authority, and the Railway Heritage Trust, will not be complete until 2025, but the public will start to see significant progress this year.
Robertson Construction North East is the principal contractor for the scheme which also benefits from the expertise of conservation architect Howarth Litchfield, project and cost manager Identity Consult, and rail specialist Principal Designer Vextrix.
Despite it being a listed Victorian building, there will be a focus on sustainability, using electricity only and installing renewable energy systems; solar panels will be positioned out of sight, in line with aims to preserve the traditional materials and aesthetic of the building.
Whilst there will unfortunately be some disruption around the station for the duration of the works, including some nighttime works on the trackside elevation, access to the railway platforms will remain open and signage will be in place to assist passengers getting to and from the trains.
Cllr Lynn Pallister, Cabinet Member for Growth and Enterprise at Redcar & Cleveland Borough Council, said:
“Our residents have been looking forward to seeing some progress on Redcar Central Station, and I know they’ll be pleased to finally see some being made.
“This is fantastic for Redcar and its local businesses as it gives visitors a more welcoming first impression of the town. In recent years we have developed some amazing leisure facilities such as a mini-golf course and a children’s play park on the seafront, a thriving cinema in The Regent, as well as the current development of sports activity hub in Beach Base and a family-friendly entertainment venue on the high street. It really is an exciting time for the area that I’m sure will encourage many more visitors.”
Tees Valley Mayor Ben Houchen said:
“This vital work will restore Redcar station to its former glory – while providing new, modern spaces for our brilliant leisure and hospitality businesses. It will encourage even more people to visit Redcar and see first-hand the fantastic new entertainment spaces while supporting the town.
“The regeneration also complements the work we’re doing at stations across the region to improve communities and give local people the transport links they deserve.”
Neil Turner, Architect and Director for Howarth Litchfield, said:
“We were delighted to win the commission for the conversion of this beautiful building which had fallen into disrepair. The innovative conversion will bring life and vitality back to the building and contribute to the council’s wider strategy of improvement in the town centre.’’
Garry Hope, Regional Managing Director, Robertson Construction North East, said:
“As the principal contractor, we have great experience of delivering high quality projects within live environments and are delighted to be delivering for Redcar & Cleveland Borough Council. The transformation of Redcar Central Station will deliver a thriving community space, and we look forward to being part of the community throughout the build.”
Timeline
-
Cabinet Approval
Redcar Central Station has finished this stageJune 2022
-
Planning and Listed Building Consent Granted
Redcar Central Station has finished this stageDecember 2022
-
PCSA Works - Surveys and Clearance
Redcar Central Station has finished this stageMarch 2023 - August 2023
-
Construction start on site
Redcar Central Station has finished this stageMay 2024
-
Saturday night possession works (trackside)
Redcar Central Station is currently at this stageAugust 2024 - March 2025
-
Construction works complete
this is an upcoming stage for Redcar Central StationAutumn 2025