We use cookies to ensure our site functions properly and to store limited information about your usage. You may give or withdraw consent at any time. To find out more, read our privacy policy and cookie policy.
Manage Cookies
A cookie is information stored on your computer by a website you visit. Cookies often store your settings for a website, such as your preferred language or location. This allows the site to present you with information customized to fit your needs. As per the GDPR law, companies need to get your explicit approval to collect your data. Some of these cookies are ‘strictly necessary’ to provide the basic functions of the website and can not be turned off, while others if present, have the option of being turned off. Learn more about our Privacy and Cookie policies. These can be managed also from our cookie policy page.
Strictly necessary cookies(always on):
Necessary for enabling core functionality. The website cannot function properly without these cookies. This cannot be turned off. e.g. Sign in, Language
Analytics cookies:
Analytical cookies help us to analyse user behaviour, mainly to see if the users are able to find and act on things that they are looking for. They allow us to recognise and count the number of visitors and to see how visitors move around our website when they are using it. Tools used: Google Analytics
King George V Playing Fields public realm and landscaping improvements
Share King George V Playing Fields public realm and landscaping improvements on FacebookShare King George V Playing Fields public realm and landscaping improvements on TwitterShare King George V Playing Fields public realm and landscaping improvements on LinkedinEmail King George V Playing Fields public realm and landscaping improvements link
King George V Playing Fields are the leisure heart of Guisborough with the leisure centre, swimming pool, bowls club, tennis club and football club all located on this site.
Proposals to improve the play provision at King George V, include a new wheeled sports facility with associated landscaping, natural play and seating features, new lighting and CCTV infrastructure to help deter anti-social behaviour, have been approved with the works due to start in summer 2026.
During spring and summer 2024, the design team hosted a series of engagement and co-design workshops with local groups, students, site users, and drop-in sessions open to anyone eager to share feedback and ideas. These collaborative sessions shaped the proposed design by prioritising community needs and preferences. In September and October 2024, the team held playback consultation sessions to unveil the masterplan design.
This spring, additional workshops with students and young people focused on developing the wheeled sports facility, exploring features and elements potential users wanted to see included within the design.
Construction is scheduled to begin in summer 2026.
Once complete, the upgraded facilities are expected to drive higher footfall across the playing fields and promote greater levels of physical activity among residents and visitors alike, delivering wider public health benefits for the Guisborough area.
Please click the Subscribe button to receive future updates for King George V Playing Fields.
King George V Playing Fields are the leisure heart of Guisborough with the leisure centre, swimming pool, bowls club, tennis club and football club all located on this site.
Proposals to improve the play provision at King George V, include a new wheeled sports facility with associated landscaping, natural play and seating features, new lighting and CCTV infrastructure to help deter anti-social behaviour, have been approved with the works due to start in summer 2026.
During spring and summer 2024, the design team hosted a series of engagement and co-design workshops with local groups, students, site users, and drop-in sessions open to anyone eager to share feedback and ideas. These collaborative sessions shaped the proposed design by prioritising community needs and preferences. In September and October 2024, the team held playback consultation sessions to unveil the masterplan design.
This spring, additional workshops with students and young people focused on developing the wheeled sports facility, exploring features and elements potential users wanted to see included within the design.
Construction is scheduled to begin in summer 2026.
Once complete, the upgraded facilities are expected to drive higher footfall across the playing fields and promote greater levels of physical activity among residents and visitors alike, delivering wider public health benefits for the Guisborough area.
Please click the Subscribe button to receive future updates for King George V Playing Fields.
Share Hi do the plans include a bike track ? Skelton & Brotton have half decent set ups. A skate park is a good idea but a focus on bicycles would be more beneficial as guisborough has great cycling links in my opinion.
Thanks for the encouraging work, I'm looking forward to it👍 on FacebookShare Hi do the plans include a bike track ? Skelton & Brotton have half decent set ups. A skate park is a good idea but a focus on bicycles would be more beneficial as guisborough has great cycling links in my opinion.
Thanks for the encouraging work, I'm looking forward to it👍 on TwitterShare Hi do the plans include a bike track ? Skelton & Brotton have half decent set ups. A skate park is a good idea but a focus on bicycles would be more beneficial as guisborough has great cycling links in my opinion.
Thanks for the encouraging work, I'm looking forward to it👍 on LinkedinEmail Hi do the plans include a bike track ? Skelton & Brotton have half decent set ups. A skate park is a good idea but a focus on bicycles would be more beneficial as guisborough has great cycling links in my opinion.
Thanks for the encouraging work, I'm looking forward to it👍 link
Hi do the plans include a bike track ? Skelton & Brotton have half decent set ups. A skate park is a good idea but a focus on bicycles would be more beneficial as guisborough has great cycling links in my opinion.
Thanks for the encouraging work, I'm looking forward to it👍
CB
asked
over 1 year ago
Hello,
Thank you for getting in touch.
Yes the design will include a pump track for wheeled sports including bike, scooters and skateboards.
Best wishes, Guisborough Levelling Up Project Team
Share Hi.this land must remane open and not fenced off. on FacebookShare Hi.this land must remane open and not fenced off. on TwitterShare Hi.this land must remane open and not fenced off. on LinkedinEmail Hi.this land must remane open and not fenced off. link
Hi.this land must remane open and not fenced off.
David doyle
asked
almost 2 years ago
Dear David,
Thank you for getting in touch.
Please note that the areas of development, for KGV Playing Fields, within this project plan are intended for community use and open to all.
Plans for the football field adjacent to Guisborough Town FC are not related to this project, therefore we are unable to comment.
Thank you.
Best wishes, Guisborough Levelling Up Project Team
Share Hi, when is the work scheduled to start and finish? on FacebookShare Hi, when is the work scheduled to start and finish? on TwitterShare Hi, when is the work scheduled to start and finish? on LinkedinEmail Hi, when is the work scheduled to start and finish? link
Hi, when is the work scheduled to start and finish?
Joanna
asked
almost 2 years ago
Dear Joanna,
Thank you for your question.
We are currently delivering public engagement sessions and collating survey responses before moving onto final designs and procuring a contractor to deliver works. We anticipate that the project will be completed by December 2025. Please check the website for further updates on timescales in the meantime. Thank you.
Best wishes, Guisborough Levelling Up Project Team
Share As mentioned, a trim trail would be extremely beneficial. As will the BMX track, stake park and the play areas. More dog waste bins to encourage dog owners to use would be helpful.
Also why are the public potentially losing a huge area of the field to Guisborough Town FC? So the club can use this area of land for a profit making business. It is pubic land. on FacebookShare As mentioned, a trim trail would be extremely beneficial. As will the BMX track, stake park and the play areas. More dog waste bins to encourage dog owners to use would be helpful.
Also why are the public potentially losing a huge area of the field to Guisborough Town FC? So the club can use this area of land for a profit making business. It is pubic land. on TwitterShare As mentioned, a trim trail would be extremely beneficial. As will the BMX track, stake park and the play areas. More dog waste bins to encourage dog owners to use would be helpful.
Also why are the public potentially losing a huge area of the field to Guisborough Town FC? So the club can use this area of land for a profit making business. It is pubic land. on LinkedinEmail As mentioned, a trim trail would be extremely beneficial. As will the BMX track, stake park and the play areas. More dog waste bins to encourage dog owners to use would be helpful.
Also why are the public potentially losing a huge area of the field to Guisborough Town FC? So the club can use this area of land for a profit making business. It is pubic land. link
As mentioned, a trim trail would be extremely beneficial. As will the BMX track, stake park and the play areas. More dog waste bins to encourage dog owners to use would be helpful.
Also why are the public potentially losing a huge area of the field to Guisborough Town FC? So the club can use this area of land for a profit making business. It is pubic land.
We are unable to comment on Guisborough Town FC’s intention regarding the adjacent football pitch to their stadium, as it is not within scope of KGV Playing Fields plans.
Thank you.
Best wishes, Guisborough Levelling Up Project Team
Share I think we should fund for a public, free Astroturf where people can just show up and have fun, we already have a playing field but the goals have no nets and the grass isn’t cut regularly so I think an Astroturf would be a great, long term addition to Guisborough as it wouldn’t need much assistance. on FacebookShare I think we should fund for a public, free Astroturf where people can just show up and have fun, we already have a playing field but the goals have no nets and the grass isn’t cut regularly so I think an Astroturf would be a great, long term addition to Guisborough as it wouldn’t need much assistance. on TwitterShare I think we should fund for a public, free Astroturf where people can just show up and have fun, we already have a playing field but the goals have no nets and the grass isn’t cut regularly so I think an Astroturf would be a great, long term addition to Guisborough as it wouldn’t need much assistance. on LinkedinEmail I think we should fund for a public, free Astroturf where people can just show up and have fun, we already have a playing field but the goals have no nets and the grass isn’t cut regularly so I think an Astroturf would be a great, long term addition to Guisborough as it wouldn’t need much assistance. link
I think we should fund for a public, free Astroturf where people can just show up and have fun, we already have a playing field but the goals have no nets and the grass isn’t cut regularly so I think an Astroturf would be a great, long term addition to Guisborough as it wouldn’t need much assistance.
Matthew
asked
almost 2 years ago
Dear Matthew,
Thank you for getting in touch and for your comments and suggestions.
Please note that new concept designs for King George V Playing Fields will be published shortly, so please do check back on this website in the coming weeks for further information on this. Thank you.
Best Wishes, Guisborough Levelling Up Project Team
Share Are there plans to include trim trail equipment in thus project? on FacebookShare Are there plans to include trim trail equipment in thus project? on TwitterShare Are there plans to include trim trail equipment in thus project? on LinkedinEmail Are there plans to include trim trail equipment in thus project? link
Are there plans to include trim trail equipment in thus project?
WendyR
asked
almost 2 years ago
Dear Wendy,
Thank you for getting in touch.
As part of the design and engagement phase, we are actively exploring several options, including outdoor play equipment. Please return to the KGV Playing Field website in future for further updates on this. Thank you.
Best wishes, Guisborough Levelling Up Project Team
Share Is the zip line getting fixed on FacebookShare Is the zip line getting fixed on TwitterShare Is the zip line getting fixed on LinkedinEmail Is the zip line getting fixed link
Is the zip line getting fixed
Connor johnson
asked
about 2 years ago
Dear Connor,
Many thanks for your response, we are currently working with our architects to engage with the wider community before drawing up any initial designs on how the area will be redeveloped.
Please do continue to check our website where we will look to present concept designs as part of our consultation process.
Best wishes, Guisborough Levelling Up Project Team