Construction Update - 17 October 2024

Works are continuing to progress well on the project. All external scaffolds are nearing completion. The roofs to all building are in the process of being stripped ready for repair works.

Internally, demolition continues to the rooms on the first floor.

The work trackside (scaffolding and repairs) are continuing to progress. Network Rail have been carrying out essential track maintenance meaning a few Saturday night work shifts have been cancelled. Work will be ongoing on Saturday evenings between 11:30pm and 08:45am. We apologise for any disturbance from these works.