What is happening to the Samuel Plimsoll Blue Plaque?

    The Samuel Plimsol Blue Plaque which was affixed to the former Marks & Spencer’s building has been safely removed and stored. The plaque will be relocated to either the new event space located on the High Street or the new Culture and Leisure Anchor Attraction building.

    Why were the additional works to the former M&S/Goodwins site not identified before the demolition started?

    A series of detailed site investigations was completed in advance of the demolition works. This included structural surveys and opening up sections of the building to investigate the condition of the surrounding walls.

    Despite this extensive survey work, there were large areas of the structures that were either inaccessible or not visible until demolition was completed. Due to the scale of the site and the nature of how the buildings were constructed, it was not possible to have known in advance the nature and scope of the additional work that would be required. This is the usual situation in similar construction sites.

    Once the former M&S and Goodwins buildings were removed, the condition of the surrounding walls and structures could be fully investigated and assessed. This additional survey work, which was always planned, identified several issues that needed to be addressed.  

    What additional work is required?

    The survey work has revealed that large sections of the neighbouring walls are in a poor a condition and require stabilisation and weatherproofing improvements. 

    Therefore the surroundings walls will need a significant amount of additional work to bring them up to the required standard, including structural steelwork and propping, cladding, re-pointing, brick repairs and re-building sections of wall. Legal processes and agreements with surrounding owners have to be finalised before this remedial work can commence. 

    All of this additional work must be undertaken before the main construction work begins.

    It looks like nothing is happening on site, why is that?

    Although there may not be a great deal of visible activity on site, work is currently continuing in behind the scenes in order to enable the next phase of works to commence.

    This ongoing work includes design work, planning submissions, ordering of steelwork and other building materials, building control applications and the conclusion of legal processes such as the Party Wall process. Earlier instigation of these legal processes (including the Party Wall process) was not possible before the buildings were demolished due to their requirement for detailed planning and designs as the basis for the agreements. Engagement with neighbouring property owners has been ongoing since the beginning of the project, including about Party Wall matters.

    Is there still money for the scheme?

    The funding for the project is still available and the current pause in works will not impact the construction and opening of the Anchor Attraction. 

    The project will improve the Redcar High Street and the Esplanade by giving people a new reason to visit these areas through creating new family entertainment facilities. The additional visitors this attracts will help to support existing local businesses and jobs in the area.

    When will construction start?

    Construction has commenced on the Anchor Attraction site, although the frame of the new building will not be visible until late Autumn.  Most of the work being undertaken until then will be groundwork infrastructure and foundations.

    What is happening on site now?

    As of September, most of the activity on site is groundwork infrastructure and foundations.

    What works have been completed so far?

    The works undertaken to date have been the demolition of the former Goodwins and Marks and Spencer buildings; the remediation of retained wall structures with steel stabilisation; and groundwork infrastructure.

    Why are the works taking so long?

    The demolition period was extended due to environmental planning restrictions which required a pause in demolition between the months of October to April; and the need to agree with neighbouring property owners and tenants the solutions for the remediation retained wall structures which required party wall agreements and works licences.  These works have now been completed allowing the main build to proceed, which will take approximately 18 months through to March 2027.